Classroom & Office Building 3

Planning, Design, & Construction Management

Details

  • Budget: $75 Million
  • GSF: 60,000
  • Method: Design–build
  • Complete: Dec 2027

Sources

Field Education & Research Center

Details

  • Budget: $4.8 Million
  • GSF: 3,364
  • Method: Design–bid–build
  • Anticipated: Fall 2025

Sources

Medical Education Building

Details

  • Budget: $300 Million
  • GSF: 203,500
  • Method: CM at Risk
  • CM: Turner Construction
  • Complete: Fall 2026

Sources

Promise Housing

Details

  • Budget: $100 Million
  • GSF: 125,000
  • Beds: 488
  • Method: Design–build
  • Complete: Aug 2026

Sources

Project Summary

Project Budget GSF Method Completion
COB3 $75 M 60,000 Design-build Dec 2027
Field Center $4.8 M 3,364 Design-bid-build Fall 2025
Medical Ed. $300 M 203,500 CM at Risk Fall 2026
Promise Housing $100 M 125,000 Design-build Aug 2026

Total Budget: $479.8 Million